(07) 3219 2777

Cement & Concrete Association of Australia

Information Note September 1995

In September, 1995, the Cement & Concrete Association of Australia released a document titled "Concrete as a Termite Barrier - Pouring Slabs to AS 2870. It is quite informative, and many of the points raised are still valid today. The document follows:

CONCRETE

INFORMATION

FROM THE CEMENT AND CONCRETE ASSOCIATION OF AUSTRALIA Sept 1995

The Association is a national non-profit organisation sponsored by the cement industry in Australia to provide information on the many uses of cement and concrete. Since the information provided is intended for general guidance only and in no way replaces the service of professional consultants on particular projects, no liability can be accepted by the Association for its use.

Concrete as a Termite Barrier

- Pouring Slabs to AS 2870

  1. Introduction

For years people have been spraying chemicals under concrete slabs to protect houses from attack by subterranean termites. On the 30th June, 1995, the two organochlorines, heptachlor and chlordane, which were used due to their long life, were banned as a result of health issues. A number of short term chemicals (eg dursban, byflex), have since been approved, but their effective life is limited, and re treatment under slabs is difficult. Note that at this stage, the use of reticulation systems have not been approved as a means of re treatment, as their capability to last the life of the structure is yet to be confirmed.

For the first time, concrete slabs have been recognised as .part of an effective' termite barrier system, to minimise the risk of termite infestation and damage to new buildings. To complete the system, service penetrations need to be protected, and some form of treatment around the perimeter of the slab also has to be provided.

For penetrations, either Termimesh or Granitgard are acceptable, whilst for slab edges, four options are available: Termimesh, Granitgard, edge exposure and vertical horizontal chemical barriers. Chemical barriers may also be used to protect service penetrations, but a complete horizontal barrier is required, and with the difficulty to retreat, this is not seen as a viable option at this Stage. These requirements are all outlined in the new Australian Standard AS 3660.1 - 1995.

The new code, AS 3660.1, specifies that to be regarded as part of the barrier system, the slab has to be constructed in accordance with Australian Standard AS 2870 -Residential Slabs and Footings. What does this require the Builder/Designer/Engineer to comply with?

2. Control of Drying Shrinkage Cracking

The intent of requiring slabs to be constructed in accordance with AS 2870, is to ensure that the concrete has been properly placed (without addition of extra water), compacted by mechanical vibration, cured, and that the correct cover has been set to the reinforcement. A few simple quality issues, aimed at ensuring that the long term drying shrinkage of the concrete is controlled.  

Controlling the drying shrinkage of the concrete, and hence the cracking associated with it, is important, because we understand that the termite species found in N.S.W. require at least a 1 mm wide crack all the way through the slab, to be able to gain entry through the slab, and into the structure above. Generally, drying shrinkage cracks are the only ones of constant width, which extend the full slab depth.

With the adoption of good concreting practices, the reinforcing fabrics given in the standard slab designs contained in AS 2870, are sufficient to control the width of drying shrinkage cracks to less than this 1 mm. Note that if alternative types of reinforcement are used, the Designer needs to consider control of possible crack widths.

One issue requiring clarification, and one which is often questioned, is the acceptable crack widths nominated in Table A2 of AS 2870. This Table, which lists damage categories for slabs, in terms of crack widths, states that crack widths up to 2 mm are acceptable. Cracks between 1 and 2 mm in width (Category 2 damage), we estimate only occur in approximately 5% of slabs. The Cement and Concrete Association is currently investigating crack widths in housing slabs to re affirm this. The Standards Committee responsible for AS 3660.1, considered that the likelihood of having a small percentage of cracks wider than 1 mm, combined with an active termite colony at the same location, was sufficiently small to still regard concrete slabs as able to minimise the risk of damage from termites.

Note that if designs outside the standard ones in AS 2870 are nominated by an Engineer, due regard to the control of drying shrinkage crack widths needs to be considered by the Designer.

3. Quality Issues

The Residential Slabs and Footings Code, is a document that basically lists standard construction  details and techniques for concrete slabs and footings. While it does not directly cover the above quality issues, in Clause 1.4, it refers to Australian Standard AS 3600 -Concrete Structures. The quality issues that effect the durability and strength of concrete slabs, are given within this Standard.

Essentially, there are four main areas that need to be considered with house slabs: (a)addition of water on site, (b)compaction, (c)curing, and (d)provision and placement (cover), of reinforcement. There are many other factors that effect the strength of concrete, such as type of cement, aggregates, admixtures and temperature and so on. These are generally taken care of by ordering one of the standard strength grades of concrete; either N20, N25, N32, N40 or N50.

By addressing each of the four key quality issues listed above, the concrete slab will conform to the requirements of AS 2870, and thus be able to function as part of the termite barrier system.

4. Water/Cement Ratio

The water to cement ratio is the amount of water (litres or kg), divided by the weight of cement (kg), in the concrete mix. Normal water/cement ratios are around 0.5 (ie 150 litres of water and 300 kg of cementitious material per cubic metre of concrete), or less. To increase strength, and lower shrinkage, the water cement ratio is usually reduced to a minimum; that is, as little water as possible is used in the concrete mix. Water reducers, and high range water reducers (called superplasticisers), are admixtures which are often used to allow the water content to be decreased to a minimum, while still maintaining the required workability to allow the placement, compaction and finishing of the slab.

The addition of water on site, so as to increase workability, and make it easier for the concreter to place and finish, will cause increased shrinkage, and a loss of concrete strength. As the graph on page 3 indicates, an increase in the w/c ratio from 0.5 to 0.6, decreases the strength by about 30 per cent. Note that for a typical mix having say 300 kg of cement per cubic metre, this only requires the addition of 30 litres of water per cubic metre to reduce the strength by 30 % .

Effect of Water/Cement Ratio on Strength

In terms of shrinkage, water in a concrete mix occupies the spaces between the cement, sand and aggregate particles. The more water that is added, the further apart the particles in the concrete mix are forced. With the long term drying out of this water, increased cracking will occur as the particles tend to draw closer to each other, and fill the voids. According to the Australian Standard for the manufacture of concrete, premixed concrete suppliers are required to deliver concrete that has less than one millimeter of shrinkage per metre length of slab. However, typical values of between 0.6 and 0.65 mm per metre are obtained. Country plants using Type SL or shrinkage limited cement, should obtain even better results. If water is added at the client's instruction, the manufacturer is no

longer responsible for the performance of the concrete, either in terms of its shrinkage, or strength. That is, if cracks wider than 1mm occur due to excessive shrinkage caused by the addition of water, the premixed concrete supplier would not be responsible.

The addition of water also increases bleeding. This is the rise of free water to the surface of the concrete at the concrete finishing stage. It results from the settlement of particles in suspension. While excessive bleeding does not effect the ability of the slab to prevent entry of termites, it can  produce a number of other problems:

Excessive Bleeding can Result in:

A) Weaker surface layer of concrete-

If surface finishing is commenced prior to the evaporation of all bleed water, the excess water on the surface is mixed with the cement paste from the screeding process. This substantially increases the water/cement ratio near the surface, and results in a surface, which even though finished off well, may be very weak and easily worn or broken away. Finished concrete slabs that have "powdery" surfaces, are examples of this problem. Note that the other major contributor to powdery surfaces is lack of proper curing. Refer Section 6.

            B) Flaking Surface-

In some instances (eg hot/windy days), the rate of evaporation of water from the surface of the slab, can be greater than the rate of bleeding. This drying out of the surface can give the impression that bleeding has ceased, and finishing should be commenced. The finishing operation produces a dense, compact surface layer, which allows a much reduced rate of evaporation. Any further bleed water, not able to work its way through the compacted surface layer, can accumulate and form a thin film underneath this layer. The result is that the top 2 to 3 millimetres can ''flake'' off, as the water film prevents adequate bonding of the surface layer to the concrete substrate. This immediately destroys whatever surface finish has been achieved. Examples have occurred where 20 mm of concrete was found to be "drummy", and subsequently ''flaked off". While this is unusual, repairs can be costly. Note that finishing off before bleeding has ceased (indicated by a sheen on the surface), can produce the same result. It is very important to ensure that bleeding has ceased prior to finishing, and that on hot/windy days the concrete is adequately protected.

            C) Laitance over Surface-

This is caused by the rising bleed water carrying small particles of lime to the surface, resulting in a white staining due to the formation of calcium carbonate. This can be removed by washing with a mild hydrochloric acid solution (1 part acid to between 10 and 20 parts water). Note, it is important to thoroughly pre wet the surface initially, to prevent acid soaking in, and to thoroughly rinse the acid off afterwards. Note that a slight roughening of the surface may result, due to the acid solution etching the surface.

            D) Pockets under the reinforcement -

If the concrete is not vibrated or compacted properly, or it contains an excess of water, the settlement of particles can cause voids to form under the reinforcing wires or bars. Settlement of particles occurs because the specific gravity of the cement, sand and aggregates, is greater than that of water. As the heavier particles settle "to the bottom of the slab or beam, the water is displaced to the surface. Voids under the reinforcement have a significant effect on the bond strength between the hardened concrete and the reinforcement, and can thus seriously reduce the structural performance of the reinforced concrete member.

5. Compaction

Clause 19.1.3 of AS 3600 states that, "concrete shall be handled, placed and compacted so as to - in part (d), completely fill the formwork to the intended level, expel entrapped air, and closely

surround all reinforcement, tendons, ducts, anchorages and embedments." While the code does not state how entrapped air is to be expelled (which is not the code's function), the requirement that it must be done is there.

Compaction is a two-stage process. First, the aggregate particles are set in motion and consolidated to fill the form and give a level top surface. In the second stage, entrapped air is expelled. This description of the process is true whether compaction is carried out by rodding, tamping and similar manual methods, or when vibration is applied to the concrete. The latter, by temporarily 'liquefying' the concrete, is generally much more efficient than hand-tamping or rodding, and hence is almost universally applied on construction sites; typically with the use of poker vibrators.

It is important to recognise the two stages in the compaction process because, with vibration, initial consolidation of the concrete can often be achieved relatively quickly. The concrete liquefies and the surface levels, giving the impression that the concrete is compacted. Entrapped air takes a little longer to rise to the surface. Compaction must therefore be prolonged until all the air has been expelled, ie until air bubbles no longer appear on the surface.

Most concrete arrives on site with between 5 to 20 % entrapped air in it, as a result of batching and mixing. As much of this as possible must be removed by proper vibration. In reality, about 1.5 to 2 percent of air will remain in the final concrete, despite thorough vibration. This entrapped air exists as minute bubbles of air trapped in pockets within the aggregates. Entrapped air up to 2 percent has very little effect on the compressive strength. However, as the graph below illustrates, each 1 % of air voids in excess of this level gives approximately a 5 % loss in compressive strength. Thus if concrete is not vibrated, a strength loss up to about 20% to 25 % could occur.

Now it is often argued that a 100 mm thick ground slab does not need vibration due to the amount of movement and working that it gets during the placement and compaction operations (known as the traditional 'gumboot' vibrators ). However all concrete should be properly vibrated. Particularly the deeper structural elements such as edge beams, thickenings, and footings, which can not be efficiently compacted without the use of a proper vibrator. In order for a concrete slab to be able to perform its structural function satisfactorily, it must be given the opportunity to develop its full strength potential, and this means ensuring that all concrete elements are adequately compacted.

With respect to termites, the main issue is the honeycombing that may result with poor compaction. This makes it easier for the termites to work their way through the slab, or around physical/chemical barrier systems (especially if the concrete strength ends up being considerable lower than designed).

In terms of compaction, the difference between a good and inadequate job is only a few minutes.

Effect of Air Voids on Strength

6. Curing

The setting and hardening of concrete involves a series of chemical reactions between the cement

and water in the concrete, resulting in the growth of crystals. As these crystals grow, they mesh and lock together, binding individual particles of cement and aggregates together. It is this binding, or cementing together of the ingredients that make up the mix, that gives concrete its strength. Without water being present, the crystals can not continue to grow, and achieve their required size/length. As the crystals are thus smaller, they can not interlock as effectively, and lower concrete strengths result.

Curing is the process whereby water is retained in the concrete, to allow the hydration process, or chemical reactions producing the crystalline growth, to proceed (so that the required 28 day design strength can be achieved). Curing improves strength, eliminates surface drying shrinkage cracks, and reduces long term drying shrinkage cracking generally.

Curing is dealt with in Section 4 of AS 3600 -Design for Durability. Depending on the location of the concrete (inland, industrial area, tropical etc.), and the surface and exposure environment (enclosed within a building, in sea water etc.), an exposure classification is given to the concrete.

For exposure classification Al (residential slabs), Clause 4.4 of AS 3600 states that concrete shall be cured continuously for a minimum of 3 days. For Bl and B2 classifications, which include concrete surfaces in above-ground exterior environments (ie paths/driveways), continuous curing for a minimum of 7 days is required.

The graph on the next page indicates the effect of various degrees of curing on the strength of concrete. It can be seen that for a typical 20 MPa concrete, no curing will result in about a 30% strength loss. Pouring the concrete on a waterproof membrane provides very good curing of the bottom surface, and the strength loss thus varies from a maximum at the top surface, to zero at the bottom, depending on the thickness of the concrete, and the rate of drying out. However, it is the top surface of the slab that is important, in terms of the abrasion resistance, powdering, compressive and bond strengths, and protection of the reinforcement.

In terms of controlling the long term drying shrinkage cracking, curing ensures that the crystal growth reaches its full potential, thereby reducing the void size, and creating stronger bonds between the particles. This means that there is less potential for shrinkage to occur.

  Curing can be achieved by any of the following measures, (a) keeping the concrete wet, (b) covering the concrete with hessian or sand and keeping it wet, (c) covering with a plastic sheet, or (d) by spraying with a liquid membrane curing compound. Curing should be commenced directly after the final finishing operation, and continue for the required curing period. Note that hosing in the morning and afternoon, and letting the concrete dry out in between, achieves very little. Once the concrete is allowed to dry out, further wetting is only of marginal worth in terms of increasing strength and durability.

Further information on liquid membrane curing compounds for concrete can be found in AS 3799 - 1990 -Curing Compounds.

Remember the concrete must have water to gain strength, and must be kept continuously wet for the minimum curing period. This is particularly so with concrete mixes using blended cements, which gain strength slower, thus making them much more vulnerable to problems if poorly cured.

Effect of Curing on Strength

7. Cover to Reinforcement/Durability

Reinforcement in a concrete ground slab is used to control the width of drying shrinkage cracks, as well as for control of temperature related stresses. Its location within the slab is important if it is to  perform satisfactorily.

One of the primary functions of concrete in a reinforced concrete structure is to protect the reinforcement from corrosion. To achieve this, the concrete must cover the reinforcement to a minimum depth depending on the exposure conditions and concrete properties. Adequate concrete cover to reinforcement can only be achieved by "burying" the reinforcement to the correct depth during the concrete pour.

  For abrasion resistance, AS 3600 in Table 4.7 nominates a minimum concrete strength of 20 MPa for footpaths and residential driveways. However, to achieve durability in terms of the exposure of the concrete to the elements (ie. protection of the reinforcement), the following minimum concrete strengths are given in Clause 4.4 and 4.5, for the various exposure conditions. Note that the classifications listed below apply to exterior concrete elements such as driveways, paths and walls (if they are reinforced).

Min. f'c  Classification             Description

 

25Mpa              A2        Above ground exterior environments more than 50 kms from the coastline in non-industrial and temperate climatic zone Applies to areas out as far as Bourke and Cobar.

32 MPa                        B1             Above ground exterior environments from 1 to 50 kms from the

coastline. Also, members in fresh water, and those in industrial areas more than 50 kms from the coastline

40 MPa             B2             Above ground exterior environments within 1 km of the coast.

Also members permanently submerged in sea water.

50 MPa                         Surfaces of members in sea water tidal or splash zones.

Combined with the above minimum concrete strengths for durability, Table 4.10.3.2 gives the concrete covers to ensure protection of the reinforcement for the design life of 50 years. A2 requires 30 mm of cover, B 1 a cover of 40 mm, and B2 a cover of 45 mm.

Note that as AS 2870 and 3600 are referred to in the Building Code of Australia, the requirements set out above have become mandatory, and should be complied with. Having stated this however, the above concrete strengths and covers are seldom complied with, probably on the basis that unlike a building structure, there are no safety issues involved with a residential driveway, or major costs to replace. The need for a 50 year life for a driveway is also questionable.

8. Plastic Shrinkage Cracking

Concreting during warm and windy conditions can often result in cracking of the surface of a partially hardened concrete slab. This is due to evaporation of surface water, and is referred to as plastic shrinkage cracking. These are probably the most common types of cracks in slabs, and are often mistaken for cracks that will allow entry of termites. However they only extend down to the level of the top reinforcement, which is another reason why proper reinforcement location is important.

  Plastic shrinkage cracking can be avoided by reducing the rate of evaporation from the concrete surface. This can be done by erecting wind breaks, ensuring tbt work is under cover, or by using aliphatic alcohols or other evaporative retarders. The monograph on the next page can be used to calculate the rate of evaporation.

Note that below a rate of 0.5 kglm2/hr, no problems with surface drying shrinkage cracking should be experienced. Between 0.5 and 1.0 kglm2/hr, precautions should be considered. Above 1.0 kglm2/hr, conditions exist that promote cracking (either high wind, low humidity, and high temperatures, or a combination of all three), and protection of work is required. Alternatively, with a combination of all three factors, delaying the pour is an option that should be seriously considered.

Effect of concrete and air temperatures, relative humidity, and wind velocity on the rate of evaporation of surface moisture from concrete.

9. S ummary

  The effects of adding water, lack of compaction, and inadequate curing, are cumulative. These may be in the order of:

W/C ratio      0% -30% reduction possible depending on quantity of water added.

Compaction             Approximately 5% reduction in strength for each 1% of air voids. Typically this could be 20% to 25% if no compaction is used, with

honeycombing also allowing possible entry of termites.

Curing             up to 30% reduction in strength of the surface layer if no curing is used.

Based on the above, if good concrete practices are not used, the final concrete strength could easily end up less than half of the intended design strength. This could result in premature wearing and powdering of the surface, excessive drying shrinkage cracking, inadequate structural performance, and may even provide a means of termite entry through crackedlhoneycombed concrete of low strength. Note that termites do not eat concrete, and can not widen an existing crack, if the concrete is of good quality, and has achieved the designed strength. Thus a good quality concrete slab can provide an effective termite-proof barrier.

The adoption of a few good concreting practices will eliminate the problems which can be

experienced due to poor quality concrete in residential work, and concrete slabs will thus continue

to provide an economical and durable solution for builders and home-owners alike.

Further information on the use of Cement and Concrete can be

obtained by contacting:

Cement and Concrete Association of Australia

New South Wales Regional Office

Level 3, 33 Berry Street, North Sydney, NSW2060

02-9929 5866 (Phone)

02-9954 0068 (Fax)

C&CAA-NSW Sept 1995

 

Termite Issue     Found Termites?     Termite Inspections    Termite Treatments    

Building?    Builders    Building Practices    Granitgard    Thermographics    Fire Ants   

    Commercial Pests    Fumigation    Consultancy    Environpest    Interesting Links 

Termite Bait Boxes    Opportunity     Contact Us

Get it right the first time!

Back to Environpest Home Page